The existing roadway is deteriorating and does not have any storm drainage facilities or pedestrian facilities. PCR ranged from 50-54 (2023 Data). All parallel routes lack sidewalks, including SR 215.
Projects — TIB Project Information
TIB Project Information
City of Okanogan's 3rd Avenue Improvements
6-E-881(011)-1
6-E-881(011)-1
3rd Avenue Improvements
Irene St to Greta St
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $1,235,000
County: Okanogan | Legislative District: 7 | Project Length: 0.30 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/12/2024
Project Information
Lead Agency | OKANOGAN |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.30 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Shawn Davisson |
Contact Email | publicworks@okanogancity.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/12/2024 |
Cultural Resource Assessment | CRA |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 12/20/2023 |
Bid Auth. Approval | 01/01/2025 | |
Construction Approval | 03/01/2025 | |
Project Closeout | 10/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 142,500 | 150,000 |
Right of Way | 0 | 0 |
Total Design | 142,500 | 150,000 |
Construction Engineering | 142,500 | 150,000 |
Construction Contract | 950,000 | 1,000,000 |
Other Construction | 0 | 0 |
Total Construction | 1,092,500 | 1,150,000 |
Total TIB Funding | 1,235,000 | 1,300,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
OKANOGAN | 65,000 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 65,000 | 5.0% |
Project Description
Reconstruct 3rd Avenue from Irene Street to Greta Street. Two 11-foot HMA lanes with rolled curb and gutter on both sides will be installed, with an 8-foot gravel parking lane serving as a buffer for a 5-foot sidewalk. Storm Drainage facilities will also be installed.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |