City of Okanogan's 3rd Avenue Improvements

6-E-881(011)-1

6-E-881(011)-1
3rd Avenue Improvements

Irene St to Greta St

FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $1,235,000

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.30   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 11/12/2024

Project Information

Lead Agency OKANOGAN
Funding Year 2025
Program SCAP
Current Phase Design
Legislative District 7
Congressional District 4
Federal Route Number 9999
Project Length 0.30 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Reconstruction
Project Contact Shawn Davisson
Contact Email publicworks@okanogancity.com
TIB Engineer Andrew Beagle
Last Payment Date 11/12/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 12/20/2023
Bid Auth. Approval 01/01/2025
Construction Approval 03/01/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 142,500 150,000
Right of Way 0 0
Total Design 142,500 150,000
     
Construction Engineering 142,500 150,000
Construction Contract 950,000 1,000,000
Other Construction 0 0
Total Construction 1,092,500 1,150,000
     
Total TIB Funding 1,235,000 1,300,000

Local Funding Partners

Funding Amount Percent
OKANOGAN 65,000 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 65,000 5.0%

Project Description

Reconstruct 3rd Avenue from Irene Street to Greta Street. Two 11-foot HMA lanes with rolled curb and gutter on both sides will be installed, with an 8-foot gravel parking lane serving as a buffer for a 5-foot sidewalk. Storm Drainage facilities will also be installed.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.