 Projects — TIB Project Information

TIB Project Information

City of Okanogan's Oak Street

6-E-881(I11)-1

6-E-881(I11)-1
Oak Street

2nd Ave to Bridge e/o 1st Ave

FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $64,173

County: Okanogan   |   Legislative District: 7   |   Project Length: 0.08   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/14/2025

Project Information

Lead Agency OKANOGAN
Funding Year 2023
Program SCAP
Current Phase Audit
Legislative District 7
Congressional District 4
Federal Route Number 9202
Project Length 0.08 mi.
ADT 4,000
Functional Class Collector
Type of Work Resurfacing
Project Contact Shawn Davisson
Contact Email publicworks@okanogancity.com
TIB Engineer Andrew Beagle
Last Payment Date 02/14/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date   09/14/2023
Predesign Approval
Design Approval 01/01/2022 01/03/2022
Bid Auth. Approval 10/25/2023 09/27/2023
Construction Approval 11/08/2023 11/20/2023
Project Closeout 03/01/2025 02/11/2025
Audit Date   02/14/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 8,559 61,188
Right of Way 0 0
Total Design 8,559 61,188
     
Construction Engineering 8,559 56,504
Construction Contract 57,132 362,589
Other Construction 0 5,070
Total Construction 65,691 424,163
     
Funding Surplus - 10,077  
Total TIB Funding 64,173 485,351

Local Funding Partners

Funding Amount Percent
OKANOGAN 1,350 0.3%
WSDOT Funding 0 0.0%
Okanogan County- STBG  419,828 86.5%
 
 
 
 
 
 
 
Total Local Funding 421,178 86.8%

Project Description

Plane and overlay the roadway and upgrade pedestrian facilities. Deteriorated concrete traffic curb and gutter and sidewalk will be replaced. Curb ramps will be replaced as needed to meet ADA requirements.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments