Roadway is too narrow, has severe structural defects, and has inadequate sight distances.
Projects — TIB Project Information
TIB Project Information
City of Brewster's Old Hwy 97
6-E-876(I05)-1
6-E-876(I05)-1
Old Hwy 97
US 97 to North C/L
FY 2024 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $169,288
County: Okanogan | Legislative District: 12 | Project Length: 0.46 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | BREWSTER |
Funding Year | 2024 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 12 |
Congressional District | 4 |
Federal Route Number | E241 |
Project Length | 0.46 mi. |
ADT | 3,106 |
Functional Class | TIB Arterial |
Type of Work | Reconstruction |
Project Contact | Misty Ruiz |
Contact Email | misty.ruiz@brewsterwa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | 04/05/2023 | |
Predesign Approval | ||
Design Approval | 01/01/2023 | 12/12/2022 |
Bid Auth. Approval | 03/15/2023 | 05/09/2023 |
Construction Approval | 05/31/2023 | 08/15/2023 |
Project Closeout | 12/15/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 14,993 | 128,393 |
Right of Way | 0 | 0 |
Total Design | 14,993 | 128,393 |
Construction Engineering | 22,559 | 194,713 |
Construction Contract | 144,968 | 1,096,670 |
Other Construction | 0 | 0 |
Total Construction | 167,527 | 1,291,383 |
Funding Surplus | - 13,232 | |
Total TIB Funding | 169,288 | 1,419,776 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
BREWSTER | 22,382 | 1.6% |
WSDOT Funding | 0 | 0.0% |
Federal Funding | 1,228,106 | 86.5% |
Total Local Funding | 1,250,488 | 88.3% |
Project Description
Full reconstruction of roadway to include widening for safety shoulders, sight distance correction, striping, guardrail and provide stormwater drainage.
Existing Condition
Project Benefits
- Improves safety;
- Extends improvements;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |