Roadway conditions exhibit transverse, longitudinal and significant alligator cracking pavement rutting, and large areas of most of the road show the need for subgrade repair.
Projects — TIB Project Information
TIB Project Information
City of Warden's 1st Street North Reconstruction
6-E-866(005)-1
6-E-866(005)-1
1st Street North Reconstruction
N County Rd to Railroad tracks
FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $908,922
County: Grant | Legislative District: 13 | Project Length: 0.50 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/11/2024
Project Information
| Lead Agency | WARDEN |
| Funding Year | 2025 |
| Program | SCAP |
| Current Phase | Construction |
| Legislative District | 13 |
| Congressional District | 4 |
| Federal Route Number | 9999 |
| Project Length | 0.50 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Reconstruction |
| Project Contact | Kristine Shuler |
| Contact Email | kshuler@cityofwarden.org |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 12/11/2024 |
| Cultural Resource Assessment | CRA |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | 09/30/2024 | |
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 01/03/2024 |
| Bid Auth. Approval | 03/03/2025 | 04/09/2025 |
| Construction Approval | 05/08/2025 | 05/19/2025 |
| Project Closeout | 07/31/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 204,440 | 143,560 |
| Right of Way | 0 | 0 |
| Total Design | 204,440 | 143,560 |
| Construction Engineering | 204,440 | 77,200 |
| Construction Contract | 1,363,820 | 736,000 |
| Other Construction | 0 | 0 |
| Total Construction | 1,568,260 | 813,200 |
| Funding Surplus | - 863,778 | |
| Total TIB Funding | 908,922 | 956,760 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| WARDEN | 47,838 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 47,838 | 5.0% |
Project Description
The travel lanes will be pulverized, excavated and reconstructed per geotechnical recommendations. The subgrade will then be compacted and a new wearing course paved and matched into the existing shoulders.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||