Washington Way North is an essential route, connecting Frontage Rd to Royal Anne Drive and provides critical access route to WSDOT, USBR, and truck scale facilities along the corridor. The roadway sees a high percentage of trucks (over 40%) and is classified as a T-4 truck route. Intersection geometry are obstacles for the truck and vehicle traffic to navigate. The average PCR of the roadway in 2018 was 47.
Projects — TIB Project Information
TIB Project Information
City of George's Washington Way N
6-E-858(005)-1
6-E-858(005)-1
Washington Way N
Richmond Ave to Frontage Rd
FY 2023 Small City Arterial Program
Current Phase : Audit
Total TIB Funding : $985,373
County: Grant | Legislative District: 13 | Project Length: 0.51 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/14/2024
Project Information
Lead Agency | GEORGE |
Funding Year | 2023 |
Program | SCAP |
Current Phase | Audit |
Legislative District | 13 |
Congressional District | 4 |
Federal Route Number | 13PB |
Project Length | 0.51 mi. |
ADT | 500 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Don Entzel |
Contact Email | mayor@cityofgeorge.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/14/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2022 | 12/16/2021 |
Bid Auth. Approval | 04/28/2023 | 04/20/2023 |
Construction Approval | 05/31/2023 | 05/23/2023 |
Project Closeout | 06/30/2024 | 08/12/2024 |
Audit Date | 08/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 80,655 | 84,900 |
Right of Way | 0 | 0 |
Total Design | 80,655 | 84,900 |
Construction Engineering | 80,655 | 84,900 |
Construction Contract | 538,270 | 867,098 |
Other Construction | 0 | 336 |
Total Construction | 618,925 | 952,334 |
Funding Increase | 287,477 | |
Funding Surplus | - 1,684 | |
Total TIB Funding | 985,373 | 1,037,234 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
GEORGE | 51,861 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 51,861 | 5.0% |
Project Description
The roadway will be pulverized, graded, improved with cement treated base, and pave the roadway. Intersections with Royal Anne Drive and Frontage Road will remove existing traffic islands to better accommodate truck turning movements.
Existing Condition
Project Benefits
- Extends improvements;
- Restores structural condition
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |