McEntee Street is a T-5 truck route and sees considerable farm to market truck traffic. The roadway extends into Grant County, ultimately connects to SR-28. McEntee Street condition is poor with alligator cracking between Walnut and Chelan. This section of the roadway also lacks proper stormwater facilities and pedestrian facilities.
Projects — TIB Project Information
TIB Project Information
Town of Coulee City's McEntee Street Improvements
6-E-856(I05)-1
6-E-856(I05)-1
McEntee Street Improvements
Walnut St to Chelan St
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $124,201
County: Grant | Legislative District: 7 | Project Length: 0.21 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | COULEE CITY |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 7 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 0.21 mi. |
ADT | 750 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Natalie Garrett |
Contact Email | tcoulee@odessaoffice.com |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2024 | 01/29/2024 |
Bid Auth. Approval | 12/05/2024 | |
Construction Approval | 05/01/2025 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 14,324 | 106,100 |
Right of Way | 0 | 0 |
Total Design | 14,324 | 106,100 |
Construction Engineering | 14,324 | 106,100 |
Construction Contract | 95,553 | 707,800 |
Other Construction | 0 | 0 |
Total Construction | 109,877 | 813,900 |
Total TIB Funding | 124,201 | 920,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
COULEE CITY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
STBG | 795,799 | 86.5% |
Total Local Funding | 795,799 | 86.5% |
Project Description
Reconstruct roadway, install curb and gutter on both sides, add new sidewalk will be added on one side. It is anticipated that swales will be utilized to infiltrate stormwater and, where possible, the storm drainage system will be connected to the existing storm drain piping on Main Street.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |