Douglas Street resufacing is the highest priority for Rock Island. Douglas Street is experiencing more demand and pavement condition needs to be addressed.
Projects — TIB Project Information
TIB Project Information
City of Rock Island's Douglas Street Improvements
6-E-853(I02)-1
6-E-853(I02)-1
Douglas Street Improvements
Rock Island Rd to 3rd St SW
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $106,850
County: Douglas | Legislative District: 7 | Project Length: 0.32 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | ROCK ISLAND |
| Funding Year | 2025 |
| Program | SCAP |
| Current Phase | Design |
| Legislative District | 7 |
| Congressional District | 4 |
| Federal Route Number | 5943 |
| Project Length | 0.32 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Reconstruction |
| Project Contact | Charity Duffy |
| Contact Email | Edc@rockislandwa.gov |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | Section 106 |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 02/19/2024 |
| Bid Auth. Approval | 12/01/2025 | |
| Construction Approval | 02/01/2026 | |
| Project Closeout | 12/30/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 11,894 | 100,000 |
| Right of Way | 0 | 0 |
| Total Design | 11,894 | 100,000 |
| Construction Engineering | 6,542 | 55,000 |
| Construction Contract | 88,414 | 743,350 |
| Other Construction | 0 | 0 |
| Total Construction | 94,956 | 798,350 |
| Total TIB Funding | 106,850 | 898,350 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROCK ISLAND | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Federal Funding | 791,500 | 88.1% |
| Total Local Funding | 791,500 | 88.1% |
Project Description
Full depth reclamation and paving. Add 5' sidewalk on oneside, two 6' bike lanes, two 12' travel lanes, and storm water facilities.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||