The section of 1st Ave, from Division St to Palouse St, is a major collector and primary street providing access for east-to-west trucks, residents, and businesses. Residents use this street to access homes, workplaces, and businesses located along 1st Ave. Truck traffic uses 1st Ave to access 1-90, SR-395, and to travel east into Lincoln County. While this section of 1st Ave was reconstructed in 2000, it is rapidly deteriorating due to a lack of pavement thickness, as well as an increase in truck traffic. Additionally, in order to provide safe pedestrian travel along this section of roadway, the existing ADA ramps require replacing, and additional new ADA ramps need to be created. There is a need to connect the roadway and walkway with three (3) other previously TIB-funded projects, including 1st Ave from Division St to Cascade St (2001), 1st Ave from Division St to Jackson St (2014), and Division St from 1st Ave to 6th Ave (2014).
Projects — TIB Project Information
TIB Project Information
City of Ritzville's 1st Avenue Improvements
6-E-845(009)-1
6-E-845(009)-1
1st Avenue Improvements
Division St to Palouse St
FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $375,432
County: Adams | Legislative District: 9 | Project Length: 0.13 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/18/2024
Project Information
Lead Agency | RITZVILLE |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Construction |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | M011 |
Project Length | 0.13 mi. |
ADT | 789 |
Functional Class | Collector |
Type of Work | Reconstruction |
Project Contact | Scott Yaeger |
Contact Email | scotty@co.adams.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 10/18/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 12/11/2023 | 01/05/2024 |
Bid Auth. Approval | 05/14/2024 | 05/22/2024 |
Construction Approval | 06/30/2024 | 07/08/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 57,765 | 62,000 |
Right of Way | 0 | 0 |
Total Design | 57,765 | 62,000 |
Construction Engineering | 44,173 | 42,619 |
Construction Contract | 339,793 | 313,906 |
Other Construction | 0 | 0 |
Total Construction | 383,966 | 356,525 |
Funding Surplus | - 66,299 | |
Total TIB Funding | 375,432 | 418,525 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
RITZVILLE | 43,093 | 10.3% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 43,093 | 10.3% |
Project Description
The project will grind the existing pavement from centerline out 13 feet in each direction for a total of 26 feet wide and replace it with 3 inches of asphalt. The project then places a 1-inch overlay over the entire 40-foot width of the roadway. 6 existing ADA ramps will be replaced. Two additional ADA ramps that are needed to complete the walkway will be constructed.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |