Argonne Road connects Spokane Valley and Millwood to north Spokane County areas, within the city the road is a primary means to access neighborhoods and business. ADT of 30,000+ with heavy peak hour congestion. Pavement, sidewalks and configuration are poor.
Projects — TIB Project Information
TIB Project Information
City of Millwood's Argonne Road Reconstruction - Phase 1
6-E-166(I02)-1
6-E-166(I02)-1
Argonne Road Reconstruction - Phase 1
150 ft s/o Frederick to N of Riverway
FY 2025 Small City Arterial Program
Current Phase : Design
Total TIB Funding : $1,278,255
County: Spokane | Legislative District: 4 | Project Length: 0.32 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
Lead Agency | MILLWOOD |
Funding Year | 2025 |
Program | SCAP |
Current Phase | Design |
Legislative District | 4 |
Congressional District | 5 |
Federal Route Number | 4041 |
Project Length | 0.32 mi. |
ADT | 33,000 |
Functional Class | Principal |
Type of Work | Reconstruction |
Project Contact | Kyle Schiewe |
Contact Email | kschiewe@millwoodwa.us |
TIB Engineer | Andrew Beagle |
Last Payment Date | |
Cultural Resource Assessment | Section 106 |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 01/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2024 | 02/27/2024 |
Bid Auth. Approval | 08/10/2024 | |
Construction Approval | 09/30/2024 | |
Project Closeout | 12/31/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 397,154 |
Right of Way | 0 | 304,249 |
Total Design | 0 | 701,403 |
Construction Engineering | 0 | 361,000 |
Construction Contract | 1,278,255 | 2,404,554 |
Other Construction | 0 | 981,390 |
Total Construction | 1,278,255 | 3,746,944 |
Total TIB Funding | 1,278,255 | 4,448,347 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MILLWOOD | 315,000 | 7.1% |
WSDOT Funding | 0 | 0.0% |
SRTC CRP | 2,855,092 | 64.2% |
Total Local Funding | 3,170,092 | 97.2% |
Project Description
Reconstruct and widen roadway. Install intersection left turn lanes, construct a shared use path along the east side of the roadway (Empire and the Spokane River bridge connecting to Millwood Trail).
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |