Argonne Road connects Spokane Valley and Millwood to north Spokane County areas, within the city the road is a primary means to access neighborhoods and business. ADT of 30,000+ with heavy peak hour congestion. Pavement, sidewalks and configuration are poor.
Projects — TIB Project Information
TIB Project Information
City of Millwood's Argonne Road Reconstruction - Phase 1
6-E-166(I02)-1
6-E-166(I02)-1
Argonne Road Reconstruction - Phase 1
150 ft s/o Frederick to N of Riverway
FY 2025 Small City Arterial Program
Current Phase : Construction
Total TIB Funding : $801,070
County: Spokane | Legislative District: 4 | Project Length: 0.32 | TIB Engineer: Andrew Beagle | Last Payment Date:
Project Information
| Lead Agency | MILLWOOD |
| Funding Year | 2025 |
| Program | SCAP |
| Current Phase | Construction |
| Legislative District | 4 |
| Congressional District | 5 |
| Federal Route Number | 4041 |
| Project Length | 0.32 mi. |
| ADT | 33,000 |
| Functional Class | Principal |
| Type of Work | Reconstruction |
| Project Contact | Kyle Schiewe |
| Contact Email | kschiewe@millwoodwa.us |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | |
| Cultural Resource Assessment | Section 106 |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | 08/03/2020 | |
| Predesign Approval | ||
| Design Approval | 02/15/2024 | 02/27/2024 |
| Bid Auth. Approval | 01/01/2025 | 01/13/2025 |
| Construction Approval | 03/30/2025 | 04/18/2025 |
| Project Closeout | 02/15/2026 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 523,636 |
| Construction Contract | 1,278,255 | 2,376,641 |
| Other Construction | 0 | 0 |
| Total Construction | 1,278,255 | 2,900,277 |
| Funding Surplus | - 477,185 | |
| Total TIB Funding | 801,070 | 2,900,277 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MILLWOOD | 315,000 | 10.9% |
| WSDOT Funding | 0 | 0.0% |
| SRTC CRP | 1,784,207 | 61.5% |
| Total Local Funding | 2,099,207 | 72.4% |
Project Description
Reconstruct and widen roadway. Install intersection left turn lanes, construct a shared use path along the east side of the roadway (Empire and the Spokane River bridge connecting to Millwood Trail).
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||