Projects — TIB Project Information
TIB Project Information
City of Lynden's 2024 1st Street Overlay
3-W-839(007)-1
3-W-839(007)-1
2024 1st Street Overlay
Riverview Rd to Grover St
FY 2025 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $363,157
County: Whatcom | Legislative District: 42 | Project Length: 0.32 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/18/2025
Project Information
Lead Agency | LYNDEN |
Funding Year | 2025 |
Program | APP |
Current Phase | Audit |
Legislative District | 42 |
Congressional District | 2 |
Federal Route Number | 8160 |
Project Length | 0.32 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Mark Sandal |
Contact Email | sandalm@lyndenwa.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 02/18/2025 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2024 | 12/15/2023 |
Bid Auth. Approval | 05/01/2024 | 04/15/2024 |
Construction Approval | 06/03/2024 | 05/02/2024 |
Project Closeout | 12/30/2024 | 02/14/2025 |
Audit Date | 02/18/2025 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 89,920 | 46,653 |
Right of Way | 0 | 0 |
Total Design | 89,920 | 46,653 |
Construction Engineering | 89,920 | 63,472 |
Construction Contract | 599,466 | 403,047 |
Other Construction | 0 | 0 |
Total Construction | 689,386 | 466,519 |
Funding Surplus | - 416,149 | |
Total TIB Funding | 363,157 | 513,172 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
LYNDEN | 150,015 | 29.2% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 150,015 | 29.2% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |