The pavement condition rating of the segments are as follows Railroad Avenue - 8th St to 12th St 44 Railroad Avenue - 12th St to W C/L 52
Projects — TIB Project Information
TIB Project Information
City of Shelton's FY 2020 Overlay Project
3-W-194(004)-1
3-W-194(004)-1
FY 2020 Overlay Project
Multiple Locations
FY 2020 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $390,390
County: Mason | Legislative District: 35 | Project Length: 0.47 | TIB Engineer: Chris Langhoff | Last Payment Date: 08/14/2023
Project Information
Lead Agency | SHELTON |
Funding Year | 2020 |
Program | APP |
Current Phase | Audit |
Legislative District | 35 |
Congressional District | 10 |
Federal Route Number | 5460 |
Project Length | 0.47 mi. |
ADT | 6,348 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Craig Gregory |
Contact Email | craig@ci.shelton.wa.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | 08/14/2023 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/16/2018 | |
Delayed Project Date | 07/01/2021 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2019 | 12/26/2018 |
Bid Auth. Approval | 02/01/2022 | 01/28/2022 |
Construction Approval | 04/01/2022 | 03/11/2022 |
Project Closeout | 07/31/2023 | 08/02/2023 |
Audit Date | 08/14/2023 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 34,200 | 44,633 |
Right of Way | 0 | 0 |
Total Design | 34,200 | 44,633 |
Construction Engineering | 34,200 | 62,784 |
Construction Contract | 342,000 | 400,225 |
Other Construction | 0 | 0 |
Total Construction | 376,200 | 463,009 |
Funding Surplus | - 20,010 | |
Total TIB Funding | 390,390 | 507,642 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SHELTON | 117,252 | 23.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 117,252 | 23.1% |
Project Description
This project will include the grinding and overlaying of Railroad Avenue from 12th St. to the City limits 100'+/- beyond Pacific Ct. Crushed surfacing top course will be used to fill and level the areas adjacent to the traveled way. Non-compliant ADA curb ramps and sidewalk replacement funds are being requested through the 2018 Urban SP for the same project area. Currently, the City has three other planned construction projects that include the placement of estimated an 10,500 tons of HMA. The City will be replacing the watermain in early 2019 prior to the HMA overlay.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |