Projects — TIB Project Information
TIB Project Information
City of Port Townsend's Tyler Street Overlay
3-W-151(004)-1
3-W-151(004)-1
Tyler Street Overlay
Jefferson St to Lawrence St
FY 2024 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $379,355
County: Jefferson | Legislative District: 24 | Project Length: 0.24 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | PORT TOWNSEND |
Funding Year | 2024 |
Program | APP |
Current Phase | Design |
Legislative District | 24 |
Congressional District | 6 |
Federal Route Number | 7604 |
Project Length | 0.24 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Steve King PE |
Contact Email | sking@cityofpt.us |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2023 | 03/30/2023 |
Bid Auth. Approval | 03/30/2025 | |
Construction Approval | 04/30/2025 | |
Project Closeout | 12/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 31,605 | 37,182 |
Right of Way | 0 | 0 |
Total Design | 31,605 | 37,182 |
Construction Engineering | 31,605 | 37,182 |
Construction Contract | 316,145 | 371,935 |
Other Construction | 0 | 0 |
Total Construction | 347,750 | 409,117 |
Total TIB Funding | 379,355 | 446,299 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
PORT TOWNSEND | 66,944 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 66,944 | 15.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |