Projects — TIB Project Information
TIB Project Information
City of Sedro Woolley's 2024 N Reed Street Overlay
3-W-126(010)-1
3-W-126(010)-1
2024 N Reed Street Overlay
SR 20 to Brickyard Creek
FY 2025 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $339,389
County: Skagit | Legislative District: 39 | Project Length: 0.45 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/19/2024
Project Information
Lead Agency | SEDRO WOOLLEY |
Funding Year | 2025 |
Program | APP |
Current Phase | Construction |
Legislative District | 39 |
Congressional District | 2 |
Federal Route Number | 7379 |
Project Length | 0.45 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | David Lee |
Contact Email | dlee@sedro-woolley.gov |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/19/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2024 | 01/12/2024 |
Bid Auth. Approval | 05/16/2024 | 04/15/2024 |
Construction Approval | 05/12/2024 | 05/17/2024 |
Project Closeout | 10/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 12,750 | 8,368 |
Right of Way | 0 | 0 |
Total Design | 12,750 | 8,368 |
Construction Engineering | 21,250 | 25,000 |
Construction Contract | 443,278 | 370,914 |
Other Construction | 0 | 0 |
Total Construction | 464,528 | 395,914 |
Funding Surplus | - 137,889 | |
Total TIB Funding | 339,389 | 404,282 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
SEDRO WOOLLEY | 64,893 | 16.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 64,893 | 16.1% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |