City of Sedro Woolley's 2024 N Reed Street Overlay
3-W-126(010)-1
3-W-126(010)-1
2024 N Reed Street Overlay
SR 20 to Brickyard Creek
FY 2025 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $319,984
County: Skagit | Legislative District: 39 | Project Length: 0.45 | TIB Engineer: Chris Langhoff | Last Payment Date: 02/25/2025
Project Information
| Lead Agency | SEDRO WOOLLEY |
| Funding Year | 2025 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 39 |
| Congressional District | 2 |
| Federal Route Number | 7379 |
| Project Length | 0.45 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | David Lee |
| Contact Email | dlee@sedro-woolley.gov |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 02/25/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2024 | 01/12/2024 |
| Bid Auth. Approval | 05/16/2024 | 04/15/2024 |
| Construction Approval | 05/12/2024 | 05/17/2024 |
| Project Closeout | 12/31/2024 | 01/09/2025 |
| Audit Date | 02/25/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 12,750 | 7,704 |
| Right of Way | 0 | 0 |
| Total Design | 12,750 | 7,704 |
| Construction Engineering | 21,250 | 8,585 |
| Construction Contract | 443,278 | 360,163 |
| Other Construction | 0 | 0 |
| Total Construction | 464,528 | 368,748 |
| Funding Surplus | - 157,294 | |
| Total TIB Funding | 319,984 | 376,452 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SEDRO WOOLLEY | 56,468 | 15.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 56,468 | 15.0% |
Project Description
2 inch overlay
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||