Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Stanwood's 2024 Overlay

3-P-823(009)-1

3-P-823(009)-1
2024 Overlay

Multiple Locations

FY 2025 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $547,263

County: Snohomish   |   Legislative District: 10   |   Project Length: 0.79   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency STANWOOD
Funding Year 2025
Program APP
Current Phase Construction
Legislative District 10
Congressional District 2
Federal Route Number 9309
Project Length 0.79 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Alan Lytton
Contact Email alan.lytton@ci.stanwood.wa.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/01/2024 12/18/2023
Bid Auth. Approval 03/29/2024 03/07/2024
Construction Approval 03/26/2024 03/29/2024
Project Closeout 10/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 11,050 11,050
Right of Way 0 0
Total Design 11,050 11,050
     
Construction Engineering 17,000 13,745
Construction Contract 604,073 624,044
Other Construction 0 0
Total Construction 621,073 637,789
     
Funding Surplus - 84,860  
Total TIB Funding 547,263 648,839

Local Funding Partners

Funding Amount Percent
STANWOOD 101,576 15.7%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 101,576 15.7%

Project Description

Grind and 2-inch overlay of the following segments 72nd Avenue NW - 265th St NW to Pioneer Hwy with 5 ADA ramps 284th Street NW - 68th Ave NW to Copper Station Development with 4 ADA ramps

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments