City of North Bend's North Bend Way Overlay
3-P-804(006)-1
3-P-804(006)-1
North Bend Way Overlay
8th S to W C/L
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $547,359
County: King | Legislative District: 5 | Project Length: 0.61 | TIB Engineer: Greg Armstrong | Last Payment Date: 04/01/2024
Project Information
Lead Agency | NORTH BEND |
Funding Year | 2023 |
Program | APP |
Current Phase | Audit |
Legislative District | 5 |
Congressional District | 8 |
Federal Route Number | 17A2 |
Project Length | 0.61 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Dan Marcinko |
Contact Email | dmarcinko@northbendwa.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | 04/01/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/19/2021 | |
Delayed Project Date | 07/01/2024 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/05/2022 | 01/12/2022 |
Bid Auth. Approval | 04/15/2023 | 02/13/2023 |
Construction Approval | 06/15/2023 | 06/21/2023 |
Project Closeout | 06/30/2024 | 03/25/2024 |
Audit Date | 04/01/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 69,949 | 543 |
Right of Way | 0 | 0 |
Total Design | 69,949 | 543 |
Construction Engineering | 46,633 | 0 |
Construction Contract | 541,246 | 612,817 |
Other Construction | 0 | 37,399 |
Total Construction | 587,879 | 650,216 |
Funding Surplus | - 110,469 | |
Total TIB Funding | 547,359 | 650,759 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
NORTH BEND | 103,400 | 15.9% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 103,400 | 15.9% |
Project Description
Grind and 2-inch Overlay of North Bend Way - West C/L to NW 8th St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |