TIB Project Information

City of North Bend's North Bend Way Overlay

3-P-804(006)-1

3-P-804(006)-1
North Bend Way Overlay

8th S to W C/L

FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $547,359

County: King   |   Legislative District: 5   |   Project Length: 0.61   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 04/01/2024

Project Information

Lead Agency NORTH BEND
Funding Year 2023
Program APP
Current Phase Audit
Legislative District 5
Congressional District 8
Federal Route Number 17A2
Project Length 0.61 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Dan Marcinko
Contact Email dmarcinko@northbendwa.gov
TIB Engineer Greg Armstrong
Last Payment Date 04/01/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 01/05/2022 01/12/2022
Bid Auth. Approval 04/15/2023 02/13/2023
Construction Approval 06/15/2023 06/21/2023
Project Closeout 06/30/2024 03/25/2024
Audit Date   04/01/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 69,949 543
Right of Way 0 0
Total Design 69,949 543
     
Construction Engineering 46,633 0
Construction Contract 541,246 612,817
Other Construction 0 37,399
Total Construction 587,879 650,216
     
Funding Surplus - 110,469  
Total TIB Funding 547,359 650,759

Local Funding Partners

Funding Amount Percent
NORTH BEND 103,400 15.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 103,400 15.9%

Project Description

Grind and 2-inch Overlay of North Bend Way - West C/L to NW 8th St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments