Projects — TIB Project Information
TIB Project Information
City of Snohomish's Avenue D Overlay
3-P-142(008)-1
3-P-142(008)-1
Avenue D Overlay
Multiple Locations
FY 2023 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $103,219
County: Snohomish | Legislative District: 44 | Project Length: 0.09 | TIB Engineer: Greg Armstrong | Last Payment Date: 02/12/2024
Project Information
| Lead Agency | SNOHOMISH |
| Funding Year | 2023 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 44 |
| Congressional District | 1 |
| Federal Route Number | 2628 |
| Project Length | 0.09 mi. |
| ADT | 0 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Andrew Sics |
| Contact Email | sics@snohomishwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 02/12/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/19/2021 | |
| Delayed Project Date | 07/01/2024 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2022 | 01/05/2022 |
| Bid Auth. Approval | 05/15/2023 | 05/18/2023 |
| Construction Approval | 06/07/2023 | 06/19/2023 |
| Project Closeout | 01/31/2024 | 02/06/2024 |
| Audit Date | 02/12/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 4,250 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 4,250 | 0 |
| Construction Engineering | 4,250 | 0 |
| Construction Contract | 86,275 | 140,886 |
| Other Construction | 0 | 0 |
| Total Construction | 90,525 | 140,886 |
| Funding Increase | 14,216 | |
| Funding Surplus | - 5,772 | |
| Total TIB Funding | 103,219 | 140,886 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| SNOHOMISH | 37,667 | 26.7% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 37,667 | 26.7% |
Project Description
Grind and 2-inch overlay of Avenue D - 1st St to 2nd St
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||