Projects — TIB Project Information
TIB Project Information
City of Milton's 2022 Overlay Award
3-P-132(003)-1
3-P-132(003)-1
2022 Overlay Award
Multiple Locations
FY 2024 Arterial Preservation Program
Current Phase : Closeout
Total TIB Funding : $500,659
County: Pierce/King | Legislative District: 30 | Project Length: 0.71 | TIB Engineer: Greg Armstrong | Last Payment Date: 12/02/2024
Project Information
Lead Agency | MILTON |
Funding Year | 2024 |
Program | APP |
Current Phase | Closeout |
Legislative District | 30 |
Congressional District | 8 |
Federal Route Number | 3288 |
Project Length | 0.71 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Dustin Madden |
Contact Email | dmadden@cityofmilton.net |
TIB Engineer | Greg Armstrong |
Last Payment Date | 12/02/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 01/18/2023 |
Bid Auth. Approval | 07/01/2024 | 07/01/2024 |
Construction Approval | 07/23/2024 | 07/24/2024 |
Project Closeout | 12/31/2024 | 11/22/2024 |
Audit Date | 12/02/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 47,600 | 56,000 |
Right of Way | 0 | 0 |
Total Design | 47,600 | 56,000 |
Construction Engineering | 47,600 | 55,979 |
Construction Contract | 390,560 | 477,037 |
Other Construction | 0 | 0 |
Total Construction | 438,160 | 533,016 |
Funding Increase | 25,425 | |
Funding Surplus | - 10,526 | |
Total TIB Funding | 500,659 | 589,016 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MILTON | 88,357 | 15.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 88,357 | 15.0% |
Project Description
This project grinds and provides a 2-inch overlay on the following segments Milton Way - Oak St to 15th Avenue Milton Way - 15th Avenue to Juniper St - 2 ADA Ramps Porter Way - Fife Way to Milton Way
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |