City of Fircrest's 2024 Overlay

3-P-130(005)-1

3-P-130(005)-1
2024 Overlay

Multiple Locations

FY 2025 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $677,409

County: Pierce   |   Legislative District: 28   |   Project Length: 0.49   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 09/16/2024

Project Information

Lead Agency FIRCREST
Funding Year 2025
Program APP
Current Phase Design
Legislative District 28
Congressional District 10
Federal Route Number 3220
Project Length 0.49 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Tyler Bemis
Contact Email tbemis@cityoffircrest.net
TIB Engineer Greg Armstrong
Last Payment Date 09/16/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/13/2024 03/19/2024
Bid Auth. Approval 02/01/2025
Construction Approval 03/01/2025
Project Closeout 12/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 97,434 115,347
Right of Way 0 0
Total Design 97,434 115,347
     
Construction Engineering 62,140 73,565
Construction Contract 517,835 613,040
Other Construction 0 0
Total Construction 579,975 686,605
     
Total TIB Funding 677,409 801,952

Local Funding Partners

Funding Amount Percent
FIRCREST 124,543 15.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 124,543 15.5%

Project Description

Grind and 2-inch overlay of Claremont Street - Alameda Ave and 67th Ave W with 8 ADA ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.