The pavement condition rating of Orchard Street - Holly Dr to Center St 50.
Projects — TIB Project Information
TIB Project Information
City of Fircrest's 2022 Overlay Award
3-P-130(004)-1
3-P-130(004)-1
2022 Overlay Award
Multiple Locations
FY 2024 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $639,121
County: Pierce | Legislative District: 28 | Project Length: 0.33 | TIB Engineer: Greg Armstrong | Last Payment Date: 09/10/2024
Project Information
Lead Agency | FIRCREST |
Funding Year | 2024 |
Program | APP |
Current Phase | Construction |
Legislative District | 28 |
Congressional District | 10 |
Federal Route Number | 2967 |
Project Length | 0.33 mi. |
ADT | 0 |
Functional Class | Principal |
Type of Work | Resurfacing |
Project Contact | Tyler Bemis |
Contact Email | tbemis@cityoffircrest.net |
TIB Engineer | Greg Armstrong |
Last Payment Date | 09/10/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/28/2023 | 02/16/2023 |
Bid Auth. Approval | 05/01/2024 | 04/17/2024 |
Construction Approval | 06/11/2024 | 06/17/2024 |
Project Closeout | 11/30/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 84,103 | 93,400 |
Right of Way | 0 | 0 |
Total Design | 84,103 | 93,400 |
Construction Engineering | 63,682 | 82,290 |
Construction Contract | 530,685 | 551,258 |
Other Construction | 0 | 0 |
Total Construction | 594,367 | 633,548 |
Funding Surplus | - 39,349 | |
Total TIB Funding | 639,121 | 726,948 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
FIRCREST | 87,827 | 12.1% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 87,827 | 12.1% |
Project Description
This project grinds and provides a 2-inch overlay of the southbound lanes of Orchard Street 24 feet of pavement Orchard Street - Holly Dr to Center St upgrade 7 ADA Ramps
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |