City of Pacific's Ellingson Overlay

3-P-117(008)-1

3-P-117(008)-1
Ellingson Overlay

West Valley Hwy to UPRR Crossing

FY 2025 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $1,607,270

County: King/Pierce   |   Legislative District: 30   |   Project Length: 0.74   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency PACIFIC
Funding Year 2025
Program APP
Current Phase Design
Legislative District 30
Congressional District 9
Federal Route Number 1026
Project Length 0.74 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Rick Gehrke
Contact Email rgehrke@ci.pacific.wa.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/02/2024 01/23/2024
Bid Auth. Approval 01/15/2025
Construction Approval 02/15/2025
Project Closeout 08/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 205,955 228,871
Right of Way 0 0
Total Design 205,955 228,871
     
Construction Engineering 164,913 183,262
Construction Contract 1,236,402 1,373,970
Other Construction 0 0
Total Construction 1,401,315 1,557,232
     
Total TIB Funding 1,607,270 1,786,103

Local Funding Partners

Funding Amount Percent
PACIFIC 178,833 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 178,833 10.0%

Project Description

Grind and 2-inch overlay of Ellingson Road between West Valley Highway and UPRR with 11 ADA ramp upgrades.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.