City of Sunnyside's Yakima Valley Highway Overlay

3-E-179(004)-1

3-E-179(004)-1
Yakima Valley Highway Overlay

1st St to 6th St

FY 2025 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $336,252

County: Yakima   |   Legislative District: 15   |   Project Length: 0.33   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/20/2024

Project Information

Lead Agency SUNNYSIDE
Funding Year 2025
Program APP
Current Phase Construction
Legislative District 15
Congressional District 4
Federal Route Number 6340
Project Length 0.33 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Robert Layman
Contact Email rlayman@sunnyside-wa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 09/20/2024
Cultural Resource Assessment CRA

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date   03/19/2024
Predesign Approval
Design Approval 02/01/2024 01/16/2024
Bid Auth. Approval 07/01/2024 04/24/2024
Construction Approval 08/12/2024 07/22/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 48,618 66,360
Right of Way 0 0
Total Design 48,618 66,360
     
Construction Engineering 48,618 66,360
Construction Contract 328,635 304,995
Other Construction 0 0
Total Construction 377,253 371,355
     
Funding Surplus - 89,619  
Total TIB Funding 336,252 437,715

Local Funding Partners

Funding Amount Percent
SUNNYSIDE 101,463 23.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 101,463 23.2%

Project Description

2' grind and overlay with some widening that will be funded by the City.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments