Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Walla Walla's Clinton Street Overlay

3-E-176(003)-1

3-E-176(003)-1
Clinton Street Overlay

Isaacs Ave to Sumach St

FY 2025 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $301,099

County: Walla Walla   |   Legislative District: 16   |   Project Length: 0.42   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 03/17/2025

Project Information

Lead Agency WALLA WALLA
Funding Year 2025
Program APP
Current Phase Audit
Legislative District 16
Congressional District 5
Federal Route Number 7195
Project Length 0.42 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Monte Puymon PE
Contact Email mpuymon@wallawallawa.gov
TIB Engineer Jonathan Heusman
Last Payment Date 03/17/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 02/02/2024
Bid Auth. Approval 06/01/2024 05/29/2024
Construction Approval 06/22/2024 06/17/2024
Project Closeout 06/30/2025 03/14/2025
Audit Date   03/17/2025
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 131,073
Right of Way 0 0
Total Design 0 131,073
     
Construction Engineering 0 56,347
Construction Contract 400,000 771,791
Other Construction 0 9,000
Total Construction 400,000 837,138
     
Funding Surplus - 98,901  
Total TIB Funding 301,099 968,211

Local Funding Partners

Funding Amount Percent
WALLA WALLA 667,112 68.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 667,112 68.9%

Project Description

2 inch grind and inlay, crack seal and minor pavement repair. Replace non compliant ADA ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments