City of Cheney's Elm Street Overlay

3-E-168(006)-1

3-E-168(006)-1
Elm Street Overlay

6th Street Vicinity to Washington Street

FY 2025 Arterial Preservation Program
Current Phase : Construction
Total TIB Funding : $1,346,492

County: Spokane   |   Legislative District: 9   |   Project Length: 0.51   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 06/25/2025

Project Information

Lead Agency CHENEY
Funding Year 2025
Program APP
Current Phase Construction
Legislative District 9
Congressional District 5
Federal Route Number 7700
Project Length 0.51 mi.
ADT 0
Functional Class Collector
Type of Work Resurfacing
Project Contact Todd Ableman
Contact Email tableman@cityofcheney.org
TIB Engineer Andrew Beagle
Last Payment Date 06/25/2025
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/18/2024 02/26/2024
Bid Auth. Approval 02/15/2025 04/24/2025
Construction Approval 05/25/2025 05/30/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 152,623 126,000
Right of Way 0 0
Total Design 152,623 126,000
     
Construction Engineering 206,041 189,460
Construction Contract 1,526,228 1,184,632
Other Construction 0 0
Total Construction 1,732,269 1,374,092
     
Funding Surplus - 538,400  
Total TIB Funding 1,346,492 1,500,092

Local Funding Partners

Funding Amount Percent
CHENEY 153,600 10.2%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 153,600 10.2%

Project Description

Preservation work includes asphalt patch repairs, crack sealing, curb tapper grinding, asphalt overlay, ADA compliance sidewalk ramps within bulbouts, and street striping.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments