City of Ephrata's Nat Washington Way Overlay

3-E-164(007)-1

3-E-164(007)-1
Nat Washington Way Overlay

A Street SE to 2nd Ave SE

FY 2024 Arterial Preservation Program
Current Phase : Design
Total TIB Funding : $563,134

County: Grant   |   Legislative District: 13   |   Project Length: 0.39   |   TIB Engineer: Andrew Beagle   |   Last Payment Date: 02/01/2024

Project Information

Lead Agency EPHRATA
Funding Year 2024
Program APP
Current Phase Design
Legislative District 13
Congressional District 4
Federal Route Number 6480
Project Length 0.39 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Rob Harris
Contact Email rharris@ephrata.org
TIB Engineer Andrew Beagle
Last Payment Date 02/01/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 01/03/2022
Bid Auth. Approval 02/15/2024
Construction Approval 04/01/2024
Project Closeout 10/30/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 86,580 96,200
Right of Way 0 0
Total Design 86,580 96,200
     
Construction Engineering 43,290 48,100
Construction Contract 433,264 481,405
Other Construction 0 0
Total Construction 476,554 529,505
     
Total TIB Funding 563,134 625,705

Local Funding Partners

Funding Amount Percent
EPHRATA 62,571 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 62,571 10.0%

Project Description

Digouts, crack sealing where needed. Grind and overlay. Replace noncompliant curb ramps and curbing. Nat Washington Way - A St SE to 2nd Ave SE

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments