Pavement due for resurfacing, road diet possibilities.
Projects — TIB Project Information
TIB Project Information
City of Ephrata's Nat Washington Way Overlay
3-E-164(007)-2
3-E-164(007)-2
Nat Washington Way Overlay
A Street SE to 2nd Ave SE
FY 2024 Arterial Preservation Program
Current Phase : Audit
Total TIB Funding : $31,554
County: Grant | Legislative District: 13 | Project Length: 1.32 | TIB Engineer: Andrew Beagle | Last Payment Date: 04/01/2025
Project Information
| Lead Agency | EPHRATA |
| Funding Year | 2024 |
| Program | APP |
| Current Phase | Audit |
| Legislative District | 13 |
| Congressional District | 0 |
| Federal Route Number | 6480 |
| Project Length | 1.32 mi. |
| ADT | 0 |
| Functional Class | Minor |
| Type of Work | Resurfacing |
| Project Contact | Shawn O'Brien |
| Contact Email | sobrien@ephrata.org |
| TIB Engineer | Andrew Beagle |
| Last Payment Date | 04/01/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/02/2022 | |
| Delayed Project Date | 07/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2023 | 01/03/2022 |
| Bid Auth. Approval | 09/20/2024 | 09/20/2024 |
| Construction Approval | 09/20/2024 | 09/20/2024 |
| Project Closeout | 11/30/2024 | 03/28/2025 |
| Audit Date | 04/01/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 4,500 | 2,474 |
| Construction Contract | 26,307 | 32,678 |
| Other Construction | 0 | 0 |
| Total Construction | 30,807 | 35,152 |
| Funding Increase | 747 | |
| Total TIB Funding | 31,554 | 35,152 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| EPHRATA | 3,598 | 10.2% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 3,598 | 10.2% |
Project Description
Digouts, crack sealing where needed. Staged project - this stage is prep work prior to chip seal. Nat Washington Way - A St SE to SR-282
Existing Condition
Project Benefits
- Preservation of the roadway, possible mulitmodal benefit.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||