Projects — TIB Project Information
TIB Project Information
City of Tenino's 2024 Park Avenue Overlay
2-W-977(002)-1
2-W-977(002)-1
2024 Park Avenue Overlay
6th St to Howard St
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $278,792
County: Thurston | Legislative District: 20 | Project Length: 0.38 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/14/2024
Project Information
Lead Agency | TENINO |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Audit |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | B340 |
Project Length | 0.38 mi. |
ADT | 0 |
Functional Class | Collector |
Type of Work | Resurfacing |
Project Contact | Troy Cannon |
Contact Email | tcannon@cityoftenino.org |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/14/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/08/2024 | 12/14/2023 |
Bid Auth. Approval | 04/18/2024 | 04/18/2024 |
Construction Approval | 05/31/2024 | 05/15/2024 |
Project Closeout | 11/02/2024 | 11/05/2024 |
Audit Date | 11/14/2024 | |
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 44,175 | 46,500 |
Right of Way | 0 | 0 |
Total Design | 44,175 | 46,500 |
Construction Engineering | 44,175 | 33,500 |
Construction Contract | 294,500 | 225,742 |
Other Construction | 0 | 0 |
Total Construction | 338,675 | 259,242 |
Funding Surplus | - 104,058 | |
Total TIB Funding | 278,792 | 305,742 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
TENINO | 26,950 | 8.8% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 26,950 | 8.8% |
Project Description
2 inch grind and overlay
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |