City of Stevenson's 2024 Chip Seal

2-W-974(004)-1

2-W-974(004)-1
2024 Chip Seal

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $163,740

County: Skamania   |   Legislative District: 17   |   Project Length: 1.67   |   TIB Engineer: Chris Langhoff   |   Last Payment Date:

Project Information

Lead Agency STEVENSON
Funding Year 2025
Program SCPP
Current Phase Construction
Legislative District 17
Congressional District 3
Federal Route Number 9999
Project Length 1.67 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Carolyn Sourek
Contact Email carolyn@ci.stevenson.wa.us
TIB Engineer Chris Langhoff
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2024 01/05/2024
Bid Auth. Approval 05/01/2024 01/05/2024
Construction Approval 05/31/2024 06/11/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 71,268 172,360
Other Construction 0 0
Total Construction 71,268 172,360
     
Funding Increase 92,472  
Total TIB Funding 163,740 172,360

Local Funding Partners

Funding Amount Percent
STEVENSON 8,620 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 8,620 5.0%

Project Description

Chip seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments