TIB Project Information
City of Vader's FY 2022 Seal Coat Project
2-W-967(003)-1
2-W-967(003)-1
FY 2022 Seal Coat Project
Multiple Locations
FY 2022 Small City Preservation Program
Current Phase : Withdrawn
Total TIB Funding : $0
County: Lewis | Legislative District: 20 | Project Length: 0.86 | TIB Engineer: Chris Langhoff | Last Payment Date:
Project Information
Lead Agency | VADER |
Funding Year | 2022 |
Program | SCPP |
Current Phase | Withdrawn |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.86 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Dianne Floyd |
Contact Email | vadercity@centurylink.net |
TIB Engineer | Chris Langhoff |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 11/20/2020 | |
Delayed Project Date | 07/01/2023 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2021 | 12/18/2020 |
Bid Auth. Approval | 04/15/2021 | 04/05/2021 |
Construction Approval | 05/01/2021 | 04/05/2021 |
Project Closeout | 10/31/2023 | |
Audit Date | ||
Withdrawn Date | 04/06/2023 |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 30,126 | 30,126 |
Other Construction | 0 | 0 |
Total Construction | 30,126 | 30,126 |
Total TIB Funding | 0 | 30,126 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
VADER | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Chip seal
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |