City of Morton's 2024 Red Town Initiative
2-W-961(006)-1
2-W-961(006)-1
2024 Red Town Initiative
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $783,930
County: Lewis | Legislative District: 20 | Project Length: 0.10 | TIB Engineer: Chris Langhoff | Last Payment Date: 11/01/2024
Project Information
Lead Agency | MORTON |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 20 |
Congressional District | 3 |
Federal Route Number | 9999 |
Project Length | 0.10 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Mike Meskimen |
Contact Email | mmeskimen@g-o.com |
TIB Engineer | Chris Langhoff |
Last Payment Date | 11/01/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 10/13/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 10/31/2023 | 11/02/2023 |
Bid Auth. Approval | 07/01/2024 | 06/22/2024 |
Construction Approval | 08/01/2024 | 07/19/2024 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 23,750 | 25,000 |
Right of Way | 0 | 0 |
Total Design | 23,750 | 25,000 |
Construction Engineering | 23,750 | 25,000 |
Construction Contract | 1,045,000 | 775,190 |
Other Construction | 0 | 0 |
Total Construction | 1,068,750 | 800,190 |
Funding Surplus | - 308,570 | |
Total TIB Funding | 783,930 | 825,190 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MORTON | 41,260 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 41,260 | 5.0% |
Project Description
To identify the best candidate streets in the City to perform an Otta Seal or Scrub Seal on and develop basic plans and specs for soliciting bids.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |