Projects — TIB Project Information
TIB Project Information
Town of Coupeville's 2024 Chip Seal
2-W-827(015)-1
2-W-827(015)-1
2024 Chip Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $65,066
County: Island | Legislative District: 10 | Project Length: 0.73 | TIB Engineer: Chris Langhoff | Last Payment Date: 01/14/2025
Project Information
| Lead Agency | COUPEVILLE |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 10 |
| Congressional District | 2 |
| Federal Route Number | 9999 |
| Project Length | 0.73 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Joe Grogan |
| Contact Email | publicworks@townofcoupeville.org |
| TIB Engineer | Chris Langhoff |
| Last Payment Date | 01/14/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 12/15/2023 |
| Bid Auth. Approval | 07/30/2024 | 12/15/2023 |
| Construction Approval | 08/30/2024 | 12/15/2023 |
| Project Closeout | 02/28/2025 | 01/13/2025 |
| Audit Date | 01/14/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 14,639 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 14,639 | 0 |
| Construction Engineering | 18,914 | 0 |
| Construction Contract | 149,132 | 68,490 |
| Other Construction | 0 | 0 |
| Total Construction | 168,046 | 68,490 |
| Funding Surplus | - 117,619 | |
| Total TIB Funding | 65,066 | 68,490 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| COUPEVILLE | 3,424 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 3,424 | 5.0% |
Project Description
Pre level and seal coat with fog seal
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||