City of Gold Bar's 9th Street Overlay

2-P-819(007)-1

2-P-819(007)-1
9th Street Overlay

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $191,150

County: Snohomish   |   Legislative District: 12   |   Project Length: 0.27   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency GOLD BAR
Funding Year 2025
Program SCPP
Current Phase Design
Legislative District 12
Congressional District 8
Federal Route Number 9999
Project Length 0.27 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Rich Norris
Contact Email r.norris@cityofgoldbar.us
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 12/31/2023 12/06/2023
Bid Auth. Approval 04/30/2024
Construction Approval 05/31/2024
Project Closeout 07/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 27,303 28,730
Right of Way 0 0
Total Design 27,303 28,730
     
Construction Engineering 13,656 14,370
Construction Contract 150,191 158,040
Other Construction 0 0
Total Construction 163,847 172,410
     
Total TIB Funding 191,150 201,140

Local Funding Partners

Funding Amount Percent
GOLD BAR 9,990 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 9,990 5.0%

Project Description

Grind and 2-inch overlay with upgrade 2 ADA ramps for 9th Street - SR 2 to Linda Ave

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.