The pavement condition of the following segments Ronge Street - Water St to Huggins Grieg Rd 63 1st Street and James Street - Nixon St to 3rd St 63 Nixon Street and 3rd St - Huggins Grieg Rd to James St 63 2nd Street - Nixon St to James St 63 4th Street - Nixon St to Ronge St 63
Projects — TIB Project Information
TIB Project Information
City of Roy's 2022 Seal Coat Award
2-P-814(006)-1
2-P-814(006)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $100,000
County: Pierce | Legislative District: 2 | Project Length: 0.88 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | ROY |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Design |
Legislative District | 2 |
Congressional District | 10 |
Federal Route Number | 9999 |
Project Length | 0.88 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Kimber Ivy |
Contact Email | Mayor@cityofroywa.us |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/02/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/01/2023 | 12/12/2022 |
Bid Auth. Approval | 04/15/2025 | |
Construction Approval | 05/01/2025 | |
Project Closeout | 10/01/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 5,450 | 5,450 |
Right of Way | 0 | 0 |
Total Design | 5,450 | 5,450 |
Construction Engineering | 8,050 | 8,050 |
Construction Contract | 86,500 | 86,500 |
Other Construction | 0 | 0 |
Total Construction | 94,550 | 94,550 |
Total TIB Funding | 100,000 | 100,000 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROY | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Chip Seal of the following segments Ronge Street - Water St to Huggins Grieg Rd 1st Street and James Street - Nixon St to 3rd St Nixon Street and 3rd St - Huggins Grieg Rd to James St 2nd Street - Nixon St to James St 4th Street - Nixon St to Ronge St
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |