Transportation Improvement Board
Performance Management Dashboard

 Projects — TIB Project Information

TIB Project Information

City of Roy's 2021 Overlay

2-P-814(004)-1

2-P-814(004)-1
2021 Overlay

McNaught St to Roy Elementary School

FY 2023 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $105,573

County: Pierce   |   Legislative District: 2   |   Project Length: 0.10   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/01/2023

Project Information

Lead Agency ROY
Funding Year 2023
Program SCPP
Current Phase Construction
Legislative District 2
Congressional District 10
Federal Route Number 9999
Project Length 0.10 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Kimber Ivy
Contact Email Mayor@cityofroywa.us
TIB Engineer Greg Armstrong
Last Payment Date 11/01/2023
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   11/19/2021
Delayed Project Date 07/01/2024  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2022 12/01/2021
Bid Auth. Approval 05/10/2023 05/09/2023
Construction Approval 07/07/2023 07/11/2023
Project Closeout 05/01/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 15,077 15,870
Right of Way 0 0
Total Design 15,077 15,870
     
Construction Engineering 15,077 9,775
Construction Contract 100,510 85,483
Other Construction 0 0
Total Construction 115,587 95,258
     
Funding Surplus - 25,091  
Total TIB Funding 105,573 111,128

Local Funding Partners

Funding Amount Percent
ROY 5,555 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 5,555 5.0%

Project Description

2-inch overlay and edge grind of 4th Street/Peterson Street between McNaught Street and Roy Elementary School

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments