The pavement condition of the following segments Cedar Street - Lyle St to EOR 81 1st Street E - Lyle St to Academy St 50 1st Street W - James St to EOR 63 4th Street W - McNaught St to Warren St 59 4th Street W - Nixon St to Ronge St 52 Huggins Greig Road - Warren St to 92nd Ave S 72 James Street - Cedar Street to N EOR 40 James Street - Huggins Greig Rd to 1st Street 68 Lyle Street - 1st St to Water St 81 Nixon Street - Huggins Greig Rd to 3rd St 64 Peterson Street N - Water St to 1st 81 Peterson Street S - 1st St to 4th St 81 Ronge Street - Water Street to Huggins Greig Rd 63 2nd Street - Warren Avenue to EOR 63 2nd Street - Lyle St to Peterson 60 3rd Street E - McNaught St to Academy St 68 3rd Street W - Nixon St to Warren St 64 Warrren Street - Water St to Huggins Greig Rd 63 Water Street - Warren St to James St 81
Projects — TIB Project Information
TIB Project Information
City of Roy's 2022 Seal Coat Award
2-P-814(006)-1
2-P-814(006)-1
2022 Seal Coat Award
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $265,157
County: Pierce | Legislative District: 2 | Project Length: 2.31 | TIB Engineer: Greg Armstrong | Last Payment Date: 10/14/2025
Project Information
| Lead Agency | ROY |
| Funding Year | 2024 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 2 |
| Congressional District | 10 |
| Federal Route Number | 9999 |
| Project Length | 2.31 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Kimber Ivy |
| Contact Email | Mayor@cityofroywa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 10/14/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/02/2022 | |
| Delayed Project Date | 07/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2023 | 12/12/2022 |
| Bid Auth. Approval | 04/15/2025 | 01/28/2025 |
| Construction Approval | 05/01/2025 | 01/28/2025 |
| Project Closeout | 09/30/2025 | 10/03/2025 |
| Audit Date | 10/14/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 5,450 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 5,450 | 0 |
| Construction Engineering | 8,050 | 0 |
| Construction Contract | 86,500 | 265,157 |
| Other Construction | 0 | 0 |
| Total Construction | 94,550 | 265,157 |
| Funding Increase | 165,157 | |
| Total TIB Funding | 265,157 | 265,157 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROY | 0 | 0.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 0 | 0.0% |
Project Description
Chip Seal of the following segments Cedar Street - Lyle St to EOR 1st Street E - Lyle St to Academy St 1st Street W - James St to EOR 4th Street W - McNaught St to Warren St 4th Street W - Nixon St to Ronge St Huggins Greig Road - Warren St to 92nd Ave S James Street - Cedar Street to N EOR James Street - Huggins Greig Rd to 1st Street Lyle Street - 1st St to Water St Nixon Street - Huggins Greig Rd to 3rd St Peterson Street N - Water St to 1st Peterson Street S - 1st St to 4th St Ronge Street - Water Street to Huggins Greig Rd 2nd Street - Warren Avenue to EOR 2nd Street - Lyle St to Peterson 3rd Street E - McNaught St to Academy St 3rd Street W - Nixon St to Warren St Warrren Street - Water St to Huggins Greig Rd Water Street - Warren St to James St
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||