The pavement condition rating of 4th Street/Peterson Street between McNaught Street and Roy Elementary School is 54.
Projects — TIB Project Information
TIB Project Information
City of Roy's 2021 Overlay
2-P-814(004)-1
2-P-814(004)-1
2021 Overlay
McNaught St to Roy Elementary School
FY 2023 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $102,371
County: Pierce | Legislative District: 2 | Project Length: 0.10 | TIB Engineer: Greg Armstrong | Last Payment Date: 01/29/2025
Project Information
| Lead Agency | ROY |
| Funding Year | 2023 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 2 |
| Congressional District | 10 |
| Federal Route Number | 9999 |
| Project Length | 0.10 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Kimber Ivy |
| Contact Email | Mayor@cityofroywa.us |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 01/29/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 11/19/2021 | |
| Delayed Project Date | 07/01/2024 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2022 | 12/01/2021 |
| Bid Auth. Approval | 05/10/2023 | 05/09/2023 |
| Construction Approval | 07/07/2023 | 07/11/2023 |
| Project Closeout | 01/31/2025 | 01/28/2025 |
| Audit Date | 01/29/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 15,077 | 11,443 |
| Right of Way | 0 | 0 |
| Total Design | 15,077 | 11,443 |
| Construction Engineering | 15,077 | 7,021 |
| Construction Contract | 100,510 | 89,294 |
| Other Construction | 0 | 0 |
| Total Construction | 115,587 | 96,315 |
| Funding Surplus | - 28,293 | |
| Total TIB Funding | 102,371 | 107,758 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ROY | 5,387 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 5,387 | 5.0% |
Project Description
2-inch overlay and edge grind of 4th Street/Peterson Street between McNaught Street and Roy Elementary School
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||