City of Carnation's Milwaukee Avenue Overlay
2-P-801(006)-1
2-P-801(006)-1
Milwaukee Avenue Overlay
Entwistle St to NE 50th St
FY 2025 Small City Preservation Program
Current Phase : Closeout
Total TIB Funding : $368,664
County: King | Legislative District: 12 | Project Length: 0.25 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
| Lead Agency | CARNATION |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Closeout |
| Legislative District | 12 |
| Congressional District | 8 |
| Federal Route Number | 9999 |
| Project Length | 0.25 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Lora Wilmes |
| Contact Email | lora.wilmes@carnationwa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/15/2024 | 01/08/2024 |
| Bid Auth. Approval | 04/30/2025 | 05/06/2025 |
| Construction Approval | 06/02/2025 | 06/04/2025 |
| Project Closeout | 10/31/2025 | 10/13/2025 |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 38,950 | 41,000 |
| Right of Way | 0 | 0 |
| Total Design | 38,950 | 41,000 |
| Construction Engineering | 38,950 | 27,223 |
| Construction Contract | 389,544 | 319,944 |
| Other Construction | 0 | 0 |
| Total Construction | 428,494 | 347,167 |
| Funding Surplus | - 98,780 | |
| Total TIB Funding | 368,664 | 388,167 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| CARNATION | 19,503 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 19,503 | 5.0% |
Project Description
Grind and 2 inch overlay with spot pavement repair of Milwaukee Avenue - Entwistle St to NE 50th St with 8 ADA ramps
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||