 Projects — TIB Project Information

TIB Project Information

Town of Ruston's 2024 Overlay

2-P-135(005)-1

2-P-135(005)-1
2024 Overlay

52nd to Park Ave

FY 2025 Small City Preservation Program
Current Phase : Design
Total TIB Funding : $352,222

County: Pierce   |   Legislative District: 27   |   Project Length: 0.48   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency RUSTON
Funding Year 2025
Program SCPP
Current Phase Design
Legislative District 27
Congressional District 6
Federal Route Number 9999
Project Length 0.48 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Rob White
Contact Email robw@rustonwa.org
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2024 01/26/2024
Bid Auth. Approval 02/01/2025
Construction Approval 02/28/2025
Project Closeout 10/31/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 54,188 57,040
Right of Way 0 0
Total Design 54,188 57,040
     
Construction Engineering 27,094 28,520
Construction Contract 270,940 285,200
Other Construction 0 0
Total Construction 298,034 313,720
     
Total TIB Funding 352,222 370,760

Local Funding Partners

Funding Amount Percent
RUSTON 18,538 5.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 18,538 5.0%

Project Description

2-inch grind and overlay of the following segments N Highland Street - 52nd Ave to Park Ave N Shirley Street - 52nd Ave to Park Ave

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.