TIB Project Information

City of Algona's Ellingson Road Overlay

2-P-119(007)-1

2-P-119(007)-1
Ellingson Road Overlay

Pacific Ave to UPRR

FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $704,176

County: King   |   Legislative District: 30   |   Project Length: 0.64   |   TIB Engineer: Greg Armstrong   |   Last Payment Date:

Project Information

Lead Agency ALGONA
Funding Year 2025
Program SCPP
Current Phase Construction
Legislative District 30
Congressional District 8
Federal Route Number 1026
Project Length 0.64 mi.
ADT 0
Functional Class Minor
Type of Work Resurfacing
Project Contact Jessica Griess
Contact Email jessicag@AlgonaWA.gov
TIB Engineer Greg Armstrong
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/14/2024 02/16/2024
Bid Auth. Approval 05/31/2024 05/30/2024
Construction Approval 07/02/2024 07/01/2024
Project Closeout 06/30/2025
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 78,300 79,000
Right of Way 0 0
Total Design 78,300 79,000
     
Construction Engineering 78,300 87,000
Construction Contract 522,000 620,918
Other Construction 0 0
Total Construction 600,300 707,918
     
Funding Increase 25,576  
Total TIB Funding 704,176 786,918

Local Funding Partners

Funding Amount Percent
ALGONA 82,742 10.5%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 82,742 10.5%

Project Description

Grind and 2-inch overlay with spot pavement repair of Ellingson Road - Pacific Avenue to UPRR with 8 ADA ramps.

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments