Projects — TIB Project Information
TIB Project Information
City of Algona's Ellingson Road Overlay
2-P-119(007)-1
2-P-119(007)-1
Ellingson Road Overlay
Pacific Ave to UPRR
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $704,176
County: King | Legislative District: 30 | Project Length: 0.64 | TIB Engineer: Greg Armstrong | Last Payment Date:
Project Information
Lead Agency | ALGONA |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 30 |
Congressional District | 8 |
Federal Route Number | 1026 |
Project Length | 0.64 mi. |
ADT | 0 |
Functional Class | Minor |
Type of Work | Resurfacing |
Project Contact | Jessica Griess |
Contact Email | jessicag@AlgonaWA.gov |
TIB Engineer | Greg Armstrong |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/14/2024 | 02/16/2024 |
Bid Auth. Approval | 05/31/2024 | 05/30/2024 |
Construction Approval | 07/02/2024 | 07/01/2024 |
Project Closeout | 06/30/2025 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 78,300 | 79,000 |
Right of Way | 0 | 0 |
Total Design | 78,300 | 79,000 |
Construction Engineering | 78,300 | 87,000 |
Construction Contract | 522,000 | 620,918 |
Other Construction | 0 | 0 |
Total Construction | 600,300 | 707,918 |
Funding Increase | 25,576 | |
Total TIB Funding | 704,176 | 786,918 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ALGONA | 82,742 | 10.5% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 82,742 | 10.5% |
Project Description
Grind and 2-inch overlay with spot pavement repair of Ellingson Road - Pacific Avenue to UPRR with 8 ADA ramps.
Existing Condition
Project Benefits
- The pavement condition rating of this segment of Ellingson Road is 50.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |