City of Medina's Upland Road Overlay

2-P-109(005)-1

2-P-109(005)-1
Upland Road Overlay

Overlake Drive W to NE 6th St

FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $179,032

County: King   |   Legislative District: 48   |   Project Length: 0.32   |   TIB Engineer: Greg Armstrong   |   Last Payment Date: 11/14/2024

Project Information

Lead Agency MEDINA
Funding Year 2024
Program SCPP
Current Phase Audit
Legislative District 48
Congressional District 1
Federal Route Number 9999
Project Length 0.32 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Ryan Osada
Contact Email rosada@medina-wa.gov
TIB Engineer Greg Armstrong
Last Payment Date 11/14/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/02/2022
Delayed Project Date 07/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 02/01/2023 12/12/2022
Bid Auth. Approval 02/08/2023 02/08/2023
Construction Approval 06/15/2023 06/22/2023
Project Closeout 11/30/2024 11/13/2024
Audit Date   11/14/2024
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 12,600 0
Right of Way 0 0
Total Design 12,600 0
     
Construction Engineering 8,100 35,907
Construction Contract 210,960 163,017
Other Construction 0 0
Total Construction 219,060 198,924
     
Funding Increase 1,691  
Funding Surplus - 54,319  
Total TIB Funding 179,032 198,924

Local Funding Partners

Funding Amount Percent
MEDINA 19,892 10.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 19,892 10.0%

Project Description

Grinds and provides a 2-inch overlay of Upland Road from Overlake Drive W to NE 6th St

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.