Projects — TIB Project Information
TIB Project Information
City of Medina's Upland Road Overlay
2-P-109(005)-1
2-P-109(005)-1
Upland Road Overlay
Overlake Drive W to NE 6th St
FY 2024 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $179,032
County: King | Legislative District: 48 | Project Length: 0.32 | TIB Engineer: Greg Armstrong | Last Payment Date: 11/14/2024
Project Information
| Lead Agency | MEDINA |
| Funding Year | 2024 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 48 |
| Congressional District | 1 |
| Federal Route Number | 9999 |
| Project Length | 0.32 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Ryan Osada |
| Contact Email | rosada@medina-wa.gov |
| TIB Engineer | Greg Armstrong |
| Last Payment Date | 11/14/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/02/2022 | |
| Delayed Project Date | 07/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 02/01/2023 | 12/12/2022 |
| Bid Auth. Approval | 02/08/2023 | 02/08/2023 |
| Construction Approval | 06/15/2023 | 06/22/2023 |
| Project Closeout | 11/30/2024 | 11/13/2024 |
| Audit Date | 11/14/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 12,600 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 12,600 | 0 |
| Construction Engineering | 8,100 | 35,907 |
| Construction Contract | 210,960 | 163,017 |
| Other Construction | 0 | 0 |
| Total Construction | 219,060 | 198,924 |
| Funding Increase | 1,691 | |
| Funding Surplus | - 54,319 | |
| Total TIB Funding | 179,032 | 198,924 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| MEDINA | 19,892 | 10.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 19,892 | 10.0% |
Project Description
Grinds and provides a 2-inch overlay of Upland Road from Overlake Drive W to NE 6th St
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||