Projects — TIB Project Information
TIB Project Information
City of Mabton's 2024 Otta Seal
2-E-942(006)-1
2-E-942(006)-1
2024 Otta Seal
Multiple Locations
FY 2024 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $656,777
County: Yakima | Legislative District: 15 | Project Length: 5.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 08/16/2024
Project Information
Lead Agency | MABTON |
Funding Year | 2024 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 15 |
Congressional District | 4 |
Federal Route Number | 9999 |
Project Length | 5.00 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Syylvia Sanchez |
Contact Email | sylvia.sanchez@co.yakima.wa.us |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 08/16/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/12/2022 | |
Delayed Project Date | 07/01/2025 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/20/2023 | 02/24/2023 |
Bid Auth. Approval | 05/01/2024 | 05/08/2024 |
Construction Approval | 05/15/2024 | 05/31/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 15,000 | 15,000 |
Right of Way | 0 | 0 |
Total Design | 15,000 | 15,000 |
Construction Engineering | 65,000 | 65,000 |
Construction Contract | 576,777 | 576,777 |
Other Construction | 0 | 0 |
Total Construction | 641,777 | 641,777 |
Total TIB Funding | 656,777 | 656,777 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MABTON | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Otta Seal the low volume residential streets in the City.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |