TIB Project Information

City of Kittitas's 2024 Chip Seal

2-E-931(013)-1

2-E-931(013)-1
2024 Chip Seal

Multiple Locations

FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $51,826

County: Kittitas   |   Legislative District: 13   |   Project Length: 0.38   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date: 09/16/2024

Project Information

Lead Agency KITTITAS
Funding Year 2025
Program SCPP
Current Phase Construction
Legislative District 13
Congressional District 8
Federal Route Number 9999
Project Length 0.38 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Richard Hink
Contact Email richard.hink@cityofkittitas.com
TIB Engineer Jonathan Heusman
Last Payment Date 09/16/2024
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   12/01/2023
Delayed Project Date 01/01/2025  
DAHP Assessment Date  
Predesign Approval
Design Approval 03/01/2024 01/29/2024
Bid Auth. Approval 04/15/2024 01/29/2024
Construction Approval 06/01/2024 04/01/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 22,835 54,522
Other Construction 0 0
Total Construction 22,835 54,522
     
Funding Increase 28,991  
Total TIB Funding 51,826 54,522

Local Funding Partners

Funding Amount Percent
KITTITAS 2,696 4.9%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 2,696 4.9%

Project Description

chip seal

Project Pictures

Project Delays

Delay Type Resolution Date Comments

No delayed project history.

Project Payments