City of Mesa's 2024 Chip Seal
2-E-928(005)-1
2-E-928(005)-1
2024 Chip Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $359,766
County: Franklin | Legislative District: 9 | Project Length: 5.18 | TIB Engineer: Jonathan Heusman | Last Payment Date: 09/19/2024
Project Information
Lead Agency | MESA |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 5.18 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Nathan Radach |
Contact Email | nathan@spinkeng.com |
TIB Engineer | Jonathan Heusman |
Last Payment Date | 09/19/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 01/01/2024 | 01/04/2024 |
Bid Auth. Approval | 05/01/2024 | 05/01/2024 |
Construction Approval | 05/31/2024 | 05/23/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 30,130 | 7,964 |
Right of Way | 0 | 0 |
Total Design | 30,130 | 7,964 |
Construction Engineering | 15,130 | 12,000 |
Construction Contract | 409,344 | 335,567 |
Other Construction | 0 | 4,235 |
Total Construction | 424,474 | 351,802 |
Funding Surplus | - 94,838 | |
Total TIB Funding | 359,766 | 359,766 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MESA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Chip seal, patching, striping, vinyl stop bar, vinyl crosswalk. Will include an alternate bid for Otta Seal on the same streets for just the travel lanes (20'). Depending on bids, will determine which treatment to move forward with.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |