Projects — TIB Project Information
TIB Project Information
City of Connell's 2024 Chip Seal
2-E-926(006)-1
2-E-926(006)-1
2024 Chip Seal
W Clark Street
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $113,586
County: Franklin | Legislative District: 9 | Project Length: 1.08 | TIB Engineer: Jonathan Heusman | Last Payment Date: 05/01/2025
Project Information
| Lead Agency | CONNELL |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | C116 |
| Project Length | 1.08 mi. |
| ADT | 0 |
| Functional Class | Collector |
| Type of Work | Resurfacing |
| Project Contact | Hallie Truck |
| Contact Email | htuch@connellwa.org |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 05/01/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 01/01/2024 | 01/29/2024 |
| Bid Auth. Approval | 03/01/2024 | 01/29/2024 |
| Construction Approval | 09/01/2024 | 09/19/2024 |
| Project Closeout | 04/30/2025 | 04/15/2025 |
| Audit Date | 05/01/2025 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 9,500 | 9,500 |
| Right of Way | 0 | 0 |
| Total Design | 9,500 | 9,500 |
| Construction Engineering | 9,500 | 3,253 |
| Construction Contract | 135,329 | 43,968 |
| Other Construction | 0 | 62,844 |
| Total Construction | 144,829 | 110,065 |
| Funding Surplus | - 40,743 | |
| Total TIB Funding | 113,586 | 119,565 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| CONNELL | 5,979 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 5,979 | 5.0% |
Project Description
Mob, TC, Paint Line, Chip seal, Fog Seal, and Sweeping.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||