City of Dayton's 2024 Otta Seal
2-E-924(010)-1
2-E-924(010)-1
2024 Otta Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $1,178,464
County: Columbia | Legislative District: 9 | Project Length: 5.00 | TIB Engineer: Jonathan Heusman | Last Payment Date: 10/22/2025
Project Information
| Lead Agency | DAYTON |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Construction |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 5.00 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Ryan Paulson |
| Contact Email | rpaulson@daytonwa.com |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 10/22/2025 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 10/12/2023 | |
| Delayed Project Date | 07/01/2026 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 10/20/2023 | 11/09/2023 |
| Bid Auth. Approval | 12/31/2023 | 03/18/2024 |
| Construction Approval | 04/30/2024 | 07/31/2024 |
| Project Closeout | 07/31/2025 | |
| Audit Date | ||
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 28,500 | 30,000 |
| Right of Way | 0 | 0 |
| Total Design | 28,500 | 30,000 |
| Construction Engineering | 66,500 | 70,000 |
| Construction Contract | 1,905,000 | 1,140,488 |
| Other Construction | 0 | 0 |
| Total Construction | 1,971,500 | 1,210,488 |
| Funding Surplus | - 821,536 | |
| Total TIB Funding | 1,178,464 | 1,240,488 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| DAYTON | 62,024 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 62,024 | 5.0% |
Project Description
Otta Seal on several streets throughout the City.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||