Projects — TIB Project Information
TIB Project Information
City of Asotin's 2024 Chip Seal
2-E-921(004)-1
2-E-921(004)-1
2024 Chip Seal
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Audit
Total TIB Funding : $57,480
County: Asotin | Legislative District: 9 | Project Length: 1.10 | TIB Engineer: Jonathan Heusman | Last Payment Date: 12/02/2024
Project Information
| Lead Agency | ASOTIN |
| Funding Year | 2025 |
| Program | SCPP |
| Current Phase | Audit |
| Legislative District | 9 |
| Congressional District | 5 |
| Federal Route Number | 9999 |
| Project Length | 1.10 mi. |
| ADT | 0 |
| Functional Class | TIB Arterial |
| Type of Work | Resurfacing |
| Project Contact | Bob Portlock |
| Contact Email | asotinpublicworks@cityofastoin.org |
| TIB Engineer | Jonathan Heusman |
| Last Payment Date | 12/02/2024 |
| Cultural Resource Assessment | Not Required |
Project Schedule
| Target Date | Actual Date | |
|---|---|---|
| Project Selection Date | 12/01/2023 | |
| Delayed Project Date | 01/01/2025 | |
| DAHP Assessment Date | ||
| Predesign Approval | ||
| Design Approval | 03/01/2024 | 01/25/2024 |
| Bid Auth. Approval | 05/01/2024 | 01/25/2024 |
| Construction Approval | 06/01/2024 | 06/10/2024 |
| Project Closeout | 12/31/2024 | 11/26/2024 |
| Audit Date | 12/02/2024 | |
| Withdrawn Date |
Project Funding
| TIB Funds | Project Costs | |
|---|---|---|
| Environmental Study | 0 | 0 |
| Design Study | 0 | 0 |
| Total Predesign | 0 | 0 |
| Special Study | 0 | 0 |
| Design | 0 | 0 |
| Right of Way | 0 | 0 |
| Total Design | 0 | 0 |
| Construction Engineering | 0 | 0 |
| Construction Contract | 139,440 | 60,505 |
| Other Construction | 0 | 0 |
| Total Construction | 139,440 | 60,505 |
| Funding Surplus | - 81,960 | |
| Total TIB Funding | 57,480 | 60,505 |
Local Funding Partners
| Funding Amount | Percent | |
|---|---|---|
| ASOTIN | 3,025 | 5.0% |
| WSDOT Funding | 0 | 0.0% |
| Total Local Funding | 3,025 | 5.0% |
Project Description
Chip Seal on several streets throughout the City.
Existing Condition
Project Benefits
Project Delays
| Delay Type | Resolution Date | Comments |
|---|---|---|
No delayed project history. |
||
