Projects — TIB Project Information
TIB Project Information
Town of Rosalia's 2024 Chip Seal
2-E-917(005)-1
2-E-917(005)-1
2024 Chip Seal
Multiple Locations
FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $117,600
County: Whitman | Legislative District: 9 | Project Length: 1.34 | TIB Engineer: Jonathan Heusman | Last Payment Date:
Project Information
Lead Agency | ROSALIA |
Funding Year | 2026 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 9 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 1.34 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Leland Root |
Contact Email | mayorroot@rosaliatown.org |
TIB Engineer | Jonathan Heusman |
Last Payment Date | |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 03/22/2024 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 04/30/2024 | 06/12/2024 |
Bid Auth. Approval | 06/30/2024 | 06/12/2024 |
Construction Approval | 06/30/2024 | 07/30/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 0 | 0 |
Right of Way | 0 | 0 |
Total Design | 0 | 0 |
Construction Engineering | 0 | 0 |
Construction Contract | 100,000 | 117,600 |
Other Construction | 0 | 0 |
Total Construction | 100,000 | 117,600 |
Funding Increase | 17,600 | |
Total TIB Funding | 117,600 | 117,600 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
ROSALIA | 0 | 0.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 0 | 0.0% |
Project Description
Chip seal to be performed by Whitman County and some striping.
Existing Condition
Project Benefits
Project Pictures
No images available.
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |