Town of Rosalia's 2024 Chip Seal

2-E-917(005)-1

2-E-917(005)-1
2024 Chip Seal

Multiple Locations

FY 2026 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $117,600

County: Whitman   |   Legislative District: 9   |   Project Length: 1.34   |   TIB Engineer: Jonathan Heusman   |   Last Payment Date:

Project Information

Lead Agency ROSALIA
Funding Year 2026
Program SCPP
Current Phase Construction
Legislative District 9
Congressional District 5
Federal Route Number 9999
Project Length 1.34 mi.
ADT 0
Functional Class TIB Arterial
Type of Work Resurfacing
Project Contact Leland Root
Contact Email mayorroot@rosaliatown.org
TIB Engineer Jonathan Heusman
Last Payment Date
Cultural Resource Assessment Not Required

Project Schedule

  Target Date Actual Date
Project Selection Date   03/22/2024
Delayed Project Date 07/01/2026  
DAHP Assessment Date  
Predesign Approval
Design Approval 04/30/2024 06/12/2024
Bid Auth. Approval 06/30/2024 06/12/2024
Construction Approval 06/30/2024 07/30/2024
Project Closeout 12/31/2024
Audit Date  
Withdrawn Date  

Project Funding

TIB Funds Project Costs
Environmental Study 0 0
Design Study 0 0
Total Predesign 0 0
     
Special Study 0 0
Design 0 0
Right of Way 0 0
Total Design 0 0
     
Construction Engineering 0 0
Construction Contract 100,000 117,600
Other Construction 0 0
Total Construction 100,000 117,600
     
Funding Increase 17,600  
Total TIB Funding 117,600 117,600

Local Funding Partners

Funding Amount Percent
ROSALIA 0 0.0%
WSDOT Funding 0 0.0%
 
 
 
 
 
 
 
 
Total Local Funding 0 0.0%

Project Description

Chip seal to be performed by Whitman County and some striping.

Project Pictures

No images available.

Project Delays

Delay Type Resolution Date Comments

No delayed project history.