TIB Project Information
City of Medical Lake's 2024 Scrub and Chip Seal - Red Town
2-E-897(008)-1
2-E-897(008)-1
2024 Scrub and Chip Seal - Red Town
Multiple Locations
FY 2025 Small City Preservation Program
Current Phase : Construction
Total TIB Funding : $902,129
County: Spokane | Legislative District: 6 | Project Length: 10.30 | TIB Engineer: Andrew Beagle | Last Payment Date: 11/27/2024
Project Information
Lead Agency | MEDICAL LAKE |
Funding Year | 2025 |
Program | SCPP |
Current Phase | Construction |
Legislative District | 6 |
Congressional District | 5 |
Federal Route Number | 9999 |
Project Length | 10.30 mi. |
ADT | 0 |
Functional Class | TIB Arterial |
Type of Work | Resurfacing |
Project Contact | Scott Duncan |
Contact Email | sduncan@medical-lake.org |
TIB Engineer | Andrew Beagle |
Last Payment Date | 11/27/2024 |
Cultural Resource Assessment | Not Required |
Project Schedule
Target Date | Actual Date | |
---|---|---|
Project Selection Date | 12/01/2023 | |
Delayed Project Date | 07/01/2026 | |
DAHP Assessment Date | ||
Predesign Approval | ||
Design Approval | 02/15/2024 | 01/25/2024 |
Bid Auth. Approval | 03/01/2024 | 07/03/2024 |
Construction Approval | 03/15/2024 | 07/03/2024 |
Project Closeout | 12/31/2024 | |
Audit Date | ||
Withdrawn Date |
Project Funding
TIB Funds | Project Costs | |
---|---|---|
Environmental Study | 0 | 0 |
Design Study | 0 | 0 |
Total Predesign | 0 | 0 |
Special Study | 0 | 0 |
Design | 6,888 | 0 |
Right of Way | 0 | 0 |
Total Design | 6,888 | 0 |
Construction Engineering | 5,748 | 0 |
Construction Contract | 689,493 | 949,815 |
Other Construction | 0 | 0 |
Total Construction | 695,241 | 949,815 |
Funding Increase | 200,000 | |
Total TIB Funding | 902,129 | 949,815 |
Local Funding Partners
Funding Amount | Percent | |
---|---|---|
MEDICAL LAKE | 47,686 | 5.0% |
WSDOT Funding | 0 | 0.0% |
Total Local Funding | 47,686 | 5.0% |
Project Description
Scrub seal and chip seal select streets on the network.
Existing Condition
Project Benefits
Project Delays
Delay Type | Resolution Date | Comments |
---|---|---|
No delayed project history. |